Your survey request template, lender checklist or closing guide may still point to the 2021 ALTA survey requirements. If so, it’s probably out of date. ALTA and NSPS replaced the 2021 edition with new standards that took effect on February 23, 2026. Most of the update tightens wording and leaves the basic rules in place. A few changes still affect what the surveyor looks for, what title materials the job needs and how you fill out Table A.
Buyers, developers, lenders and attorneys who already know what an ALTA/NSPS Land Title Survey is will get the most from the sections below. They cover when the older edition still applies and what changed. They also explain what to do differently when you order a survey for a property today.
When the 2021 ALTA Survey Requirements Still Apply
The 2021 standards now apply only in a narrow set of cases. NSPS guidance says contracts signed on or after February 23, 2026 must follow the 2026 standards, with very limited exceptions. A contract signed before that date but finished later can still use the 2021 edition. The surveyor, client, title company and lender should discuss that choice and spell it out in the contract.
Survey updates follow a similar rule. An update contracted after February 23, 2026 generally falls under the 2026 standards. NSPS allows one small exception. If the update ties directly to a sale that was set to close before February 23 and slipped only a little, the surveyor may reasonably use the 2021 edition. That exception doesn’t cover a new deal or an update ordered long after the cutoff.
The date you signed the contract matters more than the date of fieldwork. If you aren’t sure which edition fits your deal, ask your surveyor and title company before work starts. A written answer early on keeps the lender’s review from stalling near closing.
Five Changes That Matter Most in the 2026 Standards
NSPS names five changes as the most important ones in the new edition. Each one shifts what the surveyor checks, records or needs from the title side. The sections below cover them in order.
A clearer definition of Relative Positional Precision
Relative Positional Precision, or RPP, describes how much uncertainty exists between the measured positions of two corners on the same survey. The 2026 edition refines how the standards define it. NSPS says the change clears up confusion but doesn’t change how surveyors do the work.
Technology-neutral survey methods
The 2021 edition called for work performed “on the ground.” The 2026 version refers instead to practices the surveying profession generally recognizes as acceptable. NSPS names drones, LiDAR and future tools such as AI as examples. The new wording doesn’t lock surveyors into one method.
Clearer rules for title evidence
Under the 2021 edition, title insurers had to furnish copies of adjoining deeds. The 2026 standards drop that requirement. They also give surveyors more guidance on finding title evidence when a recent title commitment isn’t available. On a tight deal, plan for that research to start early.
Possession along the whole perimeter
Surveyors must now note evidence of possession or occupation along the entire perimeter. That rule applies no matter how close the evidence sits to the boundary line. It also applies whether or not the use seems to conflict with the record boundary. A neighbor’s fence, a gravel drive or a storage shed near the edge of the property can all land on the survey.
Verbal statements get noted
The 2026 standards clarify that surveyors must note verbal statements, often called parol statements, when someone makes them. A neighbor might tell the crew they’ve used a strip of land for years. An owner might mention an old handshake deal about a shared driveway. Those comments can matter later in a dispute, so the survey now records them.
Table A Requests Need a Fresh Review in 2026
Table A changed enough that a saved checklist from 2021 can point to the wrong item. The biggest addition is a new optional Item 20. If you select it, the surveyor adds a table to the face of the survey that summarizes important conditions found in the field. Potential encroachments across boundary lines or into easements, rights-of-way or setback areas fall into this table. The surveyor still won’t give a legal opinion or decide who owns what.
The old Item 20 still exists under a new number. It moved to Item 21, which now holds the custom items you negotiate with the surveyor. Each one gets a label such as 21(a) or 21(b). Requests for building heights, internal tax parcel lines or an engineering design survey now belong under Item 21.
ALTA and NSPS also adjusted wording in Items 11(b), 13, 15 and 19. Item 15 got the most reworking. If your lender’s form still lists “Item 20” for a custom request, the surveyor could read it as a request for the new encroachment table.
Older Survey Instructions Can Create Scope Gaps
Reusing a 2021-era request can leave holes in the scope. The standards ask that every request name a 2026 ALTA/NSPS Land Title Survey and list any Table A items you want. A loose order that just says “ALTA survey per lender” leaves too many open questions.
Several parts of the order deserve a fresh look. Confirm the edition and the optional items you need. Check who will receive the certification and who is actually paying, since the party that orders the survey isn’t always the client. Find out what title materials the surveyor will get and when they’ll arrive.
Deals change as they move along. ALTA’s FAQ notes that survey needs can shift during a transaction and recommends putting scope and Table A choices in writing. A short written scope gives everyone the same reference point if a lender adds an item halfway through.
What Clients Should Confirm Before Ordering
An ALTA/NSPS survey has to satisfy two sets of rules. The surveyor follows the national standards and Kentucky’s standards of practice for professional land surveyors in 201 KAR 18:150. When the two differ, the stricter rule controls. The 2026 Table A also notes that a state statute, administrative rule or local ordinance can require items that look optional on the form.
Most scope questions are easier to settle before the contract than after fieldwork. Bring your title company and lender into the conversation early. Then confirm these points with your surveyor:
- Which ALTA/NSPS edition applies, based on when you sign the contract
- The most current title commitment and any recorded documents you can share
- Which Table A items you need, including whether to request the new Item 20
- Any custom items under Item 21, written out in full
- The certification parties and who pays for the survey
- Any Kentucky or local rules that change the scope
Lenders and title companies often keep their own survey forms. Ask them to check that their forms reflect the 2026 numbering before fieldwork begins. Changing the scope after fieldwork can push the schedule back.
Frequently Asked Questions
Can a 2021 ALTA survey be updated under the 2026 standards?
Yes. An update contracted after February 23, 2026 generally has to meet the 2026 standards, so the surveyor brings the older work up to the new edition. The only narrow exception covers an update tied to a sale that was set to close before that date and ran slightly late. Ask your surveyor how much of the original research and fieldwork can carry over.
Did the 2026 standards change ALTA survey accuracy requirements?
Not in practice. The new edition refines the definition of Relative Positional Precision so people read it the same way. NSPS states that this clarification leaves the way surveyors perform the work unchanged.
Do the 2026 standards allow drones and LiDAR for ALTA surveys?
The standards now use technology-neutral wording that points to methods the surveying profession generally accepts. The official FAQ mentions drones, LiDAR and AI when it explains this change. Your surveyor picks the tools that fit the site, and the finished survey still has to meet the standards.